Tuesday, March 24, 2009

Parks and Recreation Director's Report

Parks and Recreation Division
Director's Report
March 2009

Park Development

Wilson/Carmel/Ruff Master Plan - Phase I is currently scheduled to include the entry drive with parking, entry monument signage, duck pond, small pavilion, amphitheater with restrooms and grass seating for 1500 persons, inclusive accessible playground, interpretive nature signage, picnic pavillion, additional landscaping and soft surface foot trails, and an eight foot wide concrete multi-use trail connection east-west to both established athletic park areas. Phase I plans and specifications are tentatively scheduled to be completed by September 2009.

Cleanup of Wilson/Carmel/Ruff tracts and western portions of Bakersfield Park - the Town Council awarded the contract for the abatement, demolition, and site cleanup on March 2. Work should begin in March and be completed by the end of April.