Friday, May 27, 2011

Construction to begin on Wilson Carmel tracts!

I got an update from Tony Nielsen, Park Development:
We will be kicking off the construction of the Wilson-Carmel Park Phase I project in a couple of weeks.  This park is not officially named yet (“Flower Mound Gardens” was not approved).  The park infrastructure should take around 12 months to complete.  We anticipate building the playground right after Phase I is complete.  See the attached images for the general direction we are headed.  Our goals for the playground are relatively the same as always: to create an accessible nature learning playground that is special and unique for our region.  We hope to kick off the design effort for this Leathers style playground sometime this Fall/Winter 2011.
So the land development and construction has to take place first then finally the playground construction can begin!

Wednesday, May 20, 2009

I've been in contact with Leathers and Associates!!!

In March, Nicholas and I visited Kids Quest playground in Mesquite.  


It is a beautiful wooden fort-like playground just like the kind I would love to have in our town.


It was community built and many of the pieces of equipment have plaques showing community donors had purchased them.  I also found a plaque that said the playground was designed by Leathers and Associates.

I was able to get in touch with Leathers and Associates and started with complimenting the playground we saw.

Michael Cohen replied to me:
Hello Kim,
I'm glad you liked the Mesquite playground so much.
 This is one of several great playgrounds our company has designed for communities in the DFW area.
 If you didn't know, all these playgrounds were built from scratch by community volunteers, with our guidance.
 Nearby for example, are Balch Springs (built 1997) and Rowlett (1998). Newer is Imagination Station in Keller, 640 Johnson Road.
 Happy play!!
I was excited to hear back from him.  I also thought, "Oooh cool!  New playgrounds to visit!"

I replied to him and told him about my hopes for this kind of playground on the WCR tracts.  I suggested that he speak to my contacts at town hall.  I also happened to mentioned my crazy mission to visit every cool park in the DFW area!

Here's his response:

Hi Kim,
I'd better not tell you about the other 50 Leathers playgrounds within a day trip of you! But here's a map of the closest ones. 
 
I am intrigued that you have already spoken to your city council and parks board. If they back you, and have a suitable site, it could really happen. Our designs do not have to be built by community volunteers. We can work with a parks department and a local contractor just as well.
Is is safe to send you this link, I wonder, of a playground we did recently in Kansas? www.flickr.com/photos/36847838@N02/sets/72157618015135124/show  Among other things, this playground is highly accessible, with poured rubber surfacing. And it is all plastic lumber, with no wood to maintain.
We are currently speaking with folks in Coppell about re-building their Leathers playground, and I expect to be visiting there within a few weeks. Perhaps you and I can arrange to meet, along with other key people in Flower Mound? You mentioned the Parks & Rec Director, for example.
Sincerely,
Michael Cohen

Wow!  I'm so freaking excited!  Nicholas loves the Coppell park and is would be awesome to have Leathers working on a playground right here in our town!  Doing the happy dance!


















Saturday, April 11, 2009

Friday, April 10, 2009

PALS Board Meeting, April 9, 2009

I attended the PALS Board meeting last night because one of the items on the agenda was discussion of their 5 year CIP (Capital Improvement Plan). The CIP is a plan for how funds will be used on future projects such as parks, streets, utilities, etc.

The PALS Board received a list a future projects that are being planned but they did not discuss how the CIP money would be spent on them. Instead they will review the list and discuss and prioritize funding at the following meeting on May 7th.

Tha Park Master Plan was last approved in 2001. The Park Master Plan must be updated every 7 years or else the town can not receive matching grant money from Texas Parks and Wildlife. I believe I heard last night that this amount could be as much as $500,000. Needless to say, the town will be working up updating and approving the Park Master Plan. I'm interested in keeping up on this progress because some of this money could potentially go towards the developments on the WCR tracts.

I've heard that a lot of the WCR tracts are to be developed with 4B money. I'd like to know more about 4B funds and how they are scheduled to be used.

I learned that the clean up for the WCR tracts will cost about $300,000 which is money coming from the 2007-2008 budget.

The phase 1 of the design for the WCR tracts will likely be performed by Dunaway and Associates and will hopefully begin soon.

Thursday, April 9, 2009

WCR Tract Clean Up Begins


The clean-up project on the Wilson, Carmel, Ruff tracts will begin today and last roughly 30 days. The attached image illustrates the park property work zone for the contractor.

The contractor's work hours are:
Mondays - Fridays: 7:00 a.m. - 7:00 p.m.
Saturdays: 9:00 a.m. - 5:00 p.m.

He will be removing all of the former residential structures, storage buildings, trash, etc. over roughly the next 30 days.

Also, there is a PALS Board meeting tonight at 7:00. There is nothing on the agenda about the WCR tracts but I did notice that they will be discussing their 5 year budget. I plan to attend to hear how the WCR tracts fit into the plan.

Thursday, March 26, 2009

Nature Is Essential For The Brain

Check out this article by Jonah Lehrer published in the Boston Globe, January 02, 2009.

How The City Hurts Your Brain...And What You Can Do About It

Tuesday, March 24, 2009

Parks and Recreation Director's Report

Parks and Recreation Division
Director's Report
March 2009

Park Development

Wilson/Carmel/Ruff Master Plan - Phase I is currently scheduled to include the entry drive with parking, entry monument signage, duck pond, small pavilion, amphitheater with restrooms and grass seating for 1500 persons, inclusive accessible playground, interpretive nature signage, picnic pavillion, additional landscaping and soft surface foot trails, and an eight foot wide concrete multi-use trail connection east-west to both established athletic park areas. Phase I plans and specifications are tentatively scheduled to be completed by September 2009.

Cleanup of Wilson/Carmel/Ruff tracts and western portions of Bakersfield Park - the Town Council awarded the contract for the abatement, demolition, and site cleanup on March 2. Work should begin in March and be completed by the end of April.